Status Report
Status Report: a short, regular update that tells stakeholders where the project stands. RAG status, Red, Amber or Green, is its headline.
In 30 seconds
- Problem
- Every Friday a PM copies numbers from Jira into a report by hand.
- Tool
- The skill reads the Jira project, counts what is done, late and blocked, and sets the status by fixed rules.
- Result
- A one-page dashboard and a five-sentence email, ready to send.
The flow
Choose a step to see what happens there.
AI does
Writes the headline, the points and the email. It never types a number or a colour.
You decide
Check the words, set the thresholds, send the email.
The three rules
| Rule | Amber | Red |
|---|---|---|
| Overdue share of open issues | 10 %+ | 20 %+ |
| Blocked open issues | 1+ | 3+ |
| Due by today and done | under 80 % | under 60 % |
You can change the thresholds for your project.
Get it
Download status-report.zip and install it like Tool 01. With the Jira connector, name the project. Without it, export the issues from Jira as CSV and attach the file.
Tested
Tested with a Jira CSV export of a demo project: numbers, status, desktop, phone and A4 print. The live Jira connector route has not been tested yet.