Weekly status
Project Atlas · CRM rollout
as of 2026-11-20
Amber
Amber: two tasks are past their due date and two are blocked, while 10 of the 12 tasks due by today are done.
10 of 24
Done
To do · In progress · Done: 8 · 6 · 10
5
Done this week
Last 7 days
2
Overdue
of 14 open issues
2
Blocked
of 14 open issues
Why this status
| Overdue share of open issues | 14 % (2/14) | Amber at ≥ 10 % · Red at ≥ 20 % |
| Blocked open issues | 2 | Amber at ≥ 1 · Red at ≥ 3 |
| Due by today and done | 83 % (10/12) | Amber at < 80 % · Red at < 60 % |
What moved
- Five tasks closed this week, including all three bugs from the first test import (ATLAS-7, ATLAS-8, ATLAS-9).
- The vendor's final migration tool (ATLAS-11) is 5 days late; the full dry run on 5 Dec (ATLAS-17) depends on it.
- Handover sessions with the old CRM admin (ATLAS-13) are 1 day late.
- The licence budget (ATLAS-12) and the Outlook integration (ATLAS-16) are blocked.
Requests
- Sponsor: get the licence budget (ATLAS-12) approved before the 10 Dec committee date.
- IT Security: approve the Outlook integration (ATLAS-16) so work can continue.
Overdue
| ATLAS-11 | Receive the final migration tool from the vendor · Leyla | 5 d late |
| ATLAS-13 | Record handover sessions with the old CRM admin · Murad | 1 d late |
Blocked
| ATLAS-12 | Approve the licence budget · Leyla | 2026-12-10 |
| ATLAS-16 | Email integration with Outlook · Murad | 2026-11-28 |
Due in the next 7 days
| ATLAS-14 | Show the mobile app design to the sales director · Leyla | 2026-11-21 |
| ATLAS-24 | Customer import template for branches · Nigar | 2026-11-24 |
| ATLAS-15 | Build the sales pipeline dashboard · Nigar | 2026-11-26 |